Benefits for Office Building
The substantial building cost due to
reduced waste can be lessened, since
the need to pay hauliers to dispose
of construction and demolition
debris is nullified with a proper waste
management scheme.
z
Sort waste for reuse and recy-
cling
z
Use precast building compo-
nents, such as façade, staircases,
semi-precast flooring, mid-land-
ings, slabs and beams, as much
as possible
z
Reuse excavated spoils or inert
waste for backfilling, slope stabi-
lisation and reclamation
z
Reuse used timber for formwork
on site
z
Development of a
. Refer to
z
Order the right amount of building
materials to be delivered at right
time to avoid unnecessary costs
z
Send the waste back through a
recycling programme
Benefits for Office Unit
Recycling of construction and
demolition waste reduces demand
for virgin resources and reduces the
environmental impacts associated with
resource extraction, processing and
transportation.
Green Strategies for Office Unit
z
Sort waste for reuse and recy-
cling
z
Development of a
z
Order the right amount of build-
ing materials to be delivered at
the right time to avoid unneces-
sary costs
DESIGN STAGE
3.1.13 Construction Waste Reduction
Figure 3.1.60 Construction and demolition waste were sorted
(Source: Hong Kong Green Building Council)
Office
UNIT
DESIGN STAGE
3.1.13 Construction Waste Reduction
before
after
Case study of Hong Kong Green
Building Council:
Sort Waste for Reuse and Recycling
Construction and demolition waste were sorted for reuse or
recycling. Bricks, lighting boxes and conduit were potentially
reused in the new office. Other waste e.g. paper, metals, wood
and plastic were collected for recycling.
In addition, 31.8% (by weight) of all building materials were
recycled, and more than 68% of construction waste was sorted
and diverted from landfills.
% of construction waste being reused/recycled:
(Total Weight of Construction Waste being Reused/Total Weight
of Construction Waste) X 100%.
= (1777.22 kg/5589.62 kg) X 100%
= 31.8%
Green Strategies for Office Building
Office
BUILDING
Office
UNIT
Construction Waste Reduction
Overview
As waste generation by the construction industry has always been a
problem of treatment and management, strategies on waste reduction
should be well planned. During planning stage, a
which includes sorting recycling, and disposal of demolition &
construction waste should be prepared to identify waste types and waste
reduction targets.
BEAM Plus NB V1.2 MA 10 & MA 11
At least 30% of construction/demolition waste is recycled.
Sorted
broken
concrete
Precast building
envelope
Precast
staircases